Low & Bonar

Candler, North Carolina

Project Summary

RIG reacted to an emergency call to help Low & Bonar back into production. In February 2020 L&B’s Filteco hot oil system’s piping became blocked with oxidized heat transfer fluid. RIG utilized a high temperature synthetic flushing fluid to clean the oxidized, thermally degraded contaminated fluid. The same unit was then used to filter replacement heat transfer fluid, allowing the plant to get running again.

(more…)

Steel Dynamics

Butler, Indiana

Project Summary

RIG provided portable vacuum dehydration equipment for side stream water and particulate removal from central lubrication systems. RIG’s unit was utilized for contamination control (without experiencing any down time) of multiple systems over a 3-month period in 2019.  RIG’s fleet of dehydrators and filtration equipment are ready to roll to your site today. For more information call 800-770-4510

(more…)

Solar Turbines Aftermarket Group

USA

Project Summary

RIG has teamed up with the Solar Aftermarket Team to identify and mitigate varnish deposits from turbines across the United States. RIG has effectively mitigated varnish from power plants within colleges, municipal power facilities, gas plants and manufacturing facilities. In most cases RIG can reduce varnish levels within a month while the system is in operation. If you are experiencing varnish in your lubricant call us today: 800-770-4510

(more…)

Linde / Praxair HyCO Plant

Clear Lake, Texas

Project Summary

RIG was contracted in December of 2019 to provide experienced personnel, equipment, materials and engineering needed for degreasing stainless steel steam and process lines located at Praxair’s Clear Lake HyCO Plant. See all precommission & reliability services
(more…)

Domtar

Espenola, Ontario

Project Summary

RIG was contracted in December 2019 to engineer and execute a steam blow of the main steam header assuring all debris was removed prior to putting the steam back on-line to the plants turbo-generator. RIG personnel executed the steam blow during the Christmas – New Year Holiday week.

Dresser Rand – Siemens

Snyder, TX

Project Summary

RIG was contracted as a partner to Dresser Rand (a Siemens Company) to perform oil flushing services on a Turbodyne Steam Turbine. (more…)

LyondellBasell

Channelview, TX

Project Summary

RIG was contracted in 2019 to provide engineering documents and flush plans in both the OP1 and MEOH Areas leading into the Spring 2020 Turnaround. RIG’s work with the local distributor and TA planners led to more effective processes in pipe spool cleaning, custom built materials, and execution of the varnish mitigation and oil flushing of seven compressors during the TA.

 

LyondellBasell

Clinton, IA

Project Summary

RIG was contracted in 2018 to engineer and execute varnish mitigation and oil flush on five compressor trains during LyondellBasell’s 2019 turnaround. (more…)

Exotic Automation & Supply

General Motors Testing Facility, Warren, MI

Project Summary

2019 Expansion of the GM Automotive test stand facility required oil flushing services of thousands of feet of new hydraulic lines ranging from 1-inch to 8-inch diameter. RIG’s custom engineered process and execution assured the lubricant and system piping exceeded servo valve cleanliness levels during commissioning.

Scroll to top