Turnkey Pre-Commissioning Services Fast-Track Plant Startup

CB&I’s St. Charles Power Station Team was looking for a single source vendor for turnkey pre-commissioning services for a fast-track project. Reliable Industrial Group’s experienced team of commercial, engineering, and field service personnel were able to provide all services, simplifying vendor management for CB&I and ultimately saving the client time & money.

PowerGen Plant GE Turbine Maintenance & Lube Oil Tank (MLOT) Cleaning

A GE Turbine system and Main Lube Oil Tank (MLOT) needed a thorough cleaning and contaminate removal to improve bearing life and protect the turbines critical parts. A lube oil flush, side-stream filtration, mechanical pipe cleaning, and varnish removal process performed, achieved an ISO particle count better than 15/14/10.

Extrusion Plant 3000-Ton Press Reservoir Cleaning & Oil Reconditioning

RIG performed oil reconditioning and tank cleaning on a 3000-Ton Press on location at an extrusion plant. The 48-hour cleaning process removed debris and returned ISO contamination to acceptable levels on a tight timeline.

Centrifugal Gas Compressor Varnish Removal & HVOF

The RIG team successfully removed varnish from a refinery’s centrifugal compressor lube oil system, achieving changing the MPC from >40 to 1. High velocity flushing combined with side streaming filtration an chemical cleaning. We were contracted to provide services on the compressor lube oil system during the turnaround. The services performed included:

  • Varnish mitigation flush with Step One Cleaner
  • Purge / particle contamination flush with virgin oil
  • Side stream filtration of final fill oil

Managed Reliability Program, Oil Analysis, and Side Stream Filtration for Injection Molding Manufacturer

RIG developed and implemented a turnkey ISO cleanliness program that increased the reliability of critical hydraulic systems for a global plastic mold injection company. The program managed 28 re-circulation hydraulic systems located in a single department of the manufacturing plant. These systems actuated sensitive valves and cylinders, with proportional directional valves being the most critical components.

The plant was experiencing issues with several electrically operated valves sticking in the closed position ever year requiring them to be rebuilt. Operating pressures of the valves were below 3000 psi. The target ISO 4406:99 cleanliness code for these systems was 17/15/11. The cleanliness program reduced maintenance, oil, and filter costs as well as prolonged the life of critical hydraulic equipment by exceeding the target cleanliness level on all 28 hydraulic systems.

Rework and Repair of Wiped Bearing Due to Previous Flushing Companies Mistake

A previous flushing provider left a flange slip screen in place during a turbine flush. The screen in front of the turbines T5 bearing starved the bearing of oil and caused $1.2 million dollars in damage. RIG’s plant reliability experts were called to find the source of the issue and help repair the damage while ensuring the system and oil lubricants were clean.

Mid-Stream Compressor Station

RIG recently completed a project for a mid-stream natural gas compressor station on a new Solar Mars 100 turbine. RIG organized a pre-job walk down and established a process and procedure document to ensure seamless job execution.

Major Petroleum Refinery Process Gas Compressor Chemical Clean & HVOF

RIG recently completed a project for a major petroleum refinery on a process compressor. The lube oil system for the compressor had never been cleaned in over 30 years of service and would benefit greatly from RIG’s services. The unit was down for a major maintenance outage which created the perfect opportunity to address the ISO cleanliness of the oil and oil system. RIG custom engineered and performed a successful reservoir and chemical cleaning coupled with a high velocity hot oil flush (HVOF) to return the system to acceptable ISO and API cleanliness specifications. In order to meet the needs of both the Reliability and Estimator stakeholders, the job was submitted with a not to exceed bid.

Multiple Turbines And New Install – Siemens and MHI Compressor Train

This case study presents a detailed overview of 11 high velocity hot oil flushes performed by RIG at a customer’s new production facility.
A multitude of contamination opportunities existed during the installation and fabrication processes of the lubrication equipment and piping. This study highlights the contamination consistently seen in lubrication systems after initial installation and the effectiveness of RIG’s high velocity hot oil flush services at removing the contamination.

Electro-Hydraulic Control System Fluid Swap

RIG recently completed a project for a major power plant by performing an electrohydraulic control (EHC) fluid change and flush. It was imperative that RIG met and exceeded the customer’s expectation and fulfilled their equipment reliability and budget needs.

On Board Cleaning of Piping Powerhouse on a Steam Turbine and Power Pack

A major chlorine manufacturer reached out after a failed attempt to perform an on board cleaning of the piping powerhouse on a steam turbine and power pack. The customer had previously attempted to perform an on-board cleaning of the piping unsuccessfully.

The dated piping design and configuration necessitated using the customer’s reservoir as well as an external reservoir to perform the chemical clean and HVOF. The following case study outlines the various stages of the chemical cleaning and HVOF including the periodic screen inspections until API 614 pipe cleanliness standards were successfully met.

High Velocity Hot Oil Flush

RIG was contacted after an alternative flush contractor was not able to achieve adequate flows to flush the Turbine. RIG was contracted to perform high velocity hot oil flush services on the Unit #1 Westinghouse 501AA located in West Pheonix

Varnish Mitigation on a Taurus 60 Gas Turbine

Solar contracted RIG to facilitate Varnish Mitigation on a Taurus 60 Gas Turbine because Membrane Patch Colorimetry (MPC) analysis on the unit showed a level of 27. RIG lowered the MPC rating from 27 to a 5.

Global Tire Manufacturer

RIG developed and implemented a turnkey ISO cleanliness program that increased the reliability of critical hydraulic systems for a global tire manufacturer. The program managed 63 re-circulation hydraulic systems located in a single department of the manufacturing plant. . ISO cleanliness program reduced maintenance, oil, and filter costs as well as prolonged the life of critical hydraulic equipment by exceeding target cleanliness levels on all 63 hydraulic systems

Scroll to top